Project Description
Main Project Equipment
1 x 99kw Hargassner ECO-PK biomass boiler
1 x 110kw Hargassner ECO-PK biomass boiler
1 x 4000ltr Cordivari accumulator vessel
Project Requirements
Provide heating and hot water to 38 new build houses via district heating network scheme.
The Results
Fuel cost saving of £6,316.00 per annum
RHI Payback of £14,610.00 per Annum for 20 years
Annual gain £21,153.00
20 year RHI + Fuel Savings gain including RPI is £691,264.00 The figure is index linked so therefore will rise with inflation
Payback period of 4 years
We were contacted to install a biomass system under a district heating network scheme. We installed 1 x 99kw and 1 x 110kw Hargassner Biomass Boilers to provide heating and hot water to 38 houses on a newbuild estate in Boat of Garten which is a small village in Aviemore in the Scottish Highlands.